What permissions/clearances are required to setup a Solar PV Plant?
A certain set of permissions need to be obtained and documents need to be submitted in order to setup a Solar PV plant. While these may vary from state-to-state, in order to get a Solar PV Project Accredited by AP State Load Dispatch Center (AP SLDC) for REC mechanism, the following are the statutory clearances and environmental clearances to be furnished:
1) Industrial Clearance
2) Land conversion (Agricultural to Non-Agricultural)
3) Environmental Clearance Certificate from APPCB, Hyderabad
4) Contract labour license from AP Labour Department
5) Fire Safety certificate from AP Fire Department
6) Latest tax receipt from the Municipal/Gram Panchayat for the factory land.
7) Auditor compliance certificate regarding fossil fuel utilization
8) Approval from Chief Electrical Inspector
Clearance from Forest department Also, all necessary approvals/agreements before start of Solar PV project construction are to be furnished as and when necessary. These include the following:
9) Land purchase
10) Power Evacuation arrangement permission letter from DISCOM
11) Confirmation of Metering Arrangement and location
12) ABT meter type, Manufacture, Model, Serial No. details for Energy Metering.
13) Copy of PPA (important as Preferential PPA projects are not eligible for REC mechanism)
14) Proposed Model and make of plant equipment
15) Undertaking for compliance with the usage of fossil fuel criteria as specified by MNRE
16) Details of Connectivity with DISCOM
17) Connectivity Diagram and Single Line Diagram of Plant
18) Details of pending court cases with APERC, Supreme Court of India, High Court of A.P. or any other courts
Any other documents requested by AP SLDC
While these are the documents that AP SLDC requires for REC project accreditation, these are typically the clearances/documents required in general for a Solar PV project.